This page shows the progress of each milestone (short-term project) of the IVCUAF Legacy Building project, including the progress towards achieving the long-term goal of raising 300 million naira and completing the building by the year 2026. Scroll down the page to view completed milestones and also contribute to this great work.
Current goal: Security Fixtures (Target: January 2025)
- We are raising 25 Million Naira for Security gates, First-floor perimeter security Doors, lights, electrical work, and plumbing, Burglary protection installation. 28%
Roofing of the Building (Completed December 2024)
- By God’s grace, we completed the roofing of the Legacy Building. Thank you! 100%
Final Decking (Completed February 2024)
- By the grace of God, we raised 26 Million Naira and exceeded our goal of 20 Million naira by March 2024. We appreciate all those who helped us rase against the then inflation to complete this milestone. 130%
Long-term goal: Raise 300 Million naira by 2026
- Raise 300 Million Naira to build the IVCU Legacy Building by the year 2026 | Amount left to complete: 221 Million Naira 26.6%
Thank you for your support since we first launched the campaign. Work is progressing and we cannot achieve this alone. Let your contribution be a part of this extraordinary journey. Our goal is to raise 300 Million Naira to build the IVCU Legacy Building by the year 2026. As we embark on this remarkable mission, we trust God’s ability to grant us success and eventual completion. Join this great movement in IVCU and let your love for the house show through your donation.