Legacy Building Campaign
Project Updates
Current Goal: Interior Furnishing, Electrical and Equipment installation
(Target: March 2026)
- As we continue to work on windows, doors and completion of plastering, we are also looking forward to getting started with ceiling, suspended POP and woodwork for interiors. 46%
This page shows the progress of each milestone (short-term project) of the IVCUAF Legacy Building project, including the progress towards achieving the long-term goal of raising 300 million naira and completing the building by the year 2026. Scroll down the page to view completed milestones and also contribute to this great work.
Click to view the Interactive dashboard below
Windows installations for first floor and ground floor (Completed July 2025)
- 100%
Interior and Exterior Plaster (Completed March 2025)
- 100%
Roofing of the Building (Completed December 2024)
- By God’s grace, we completed the roofing of the Legacy Building. Thank you! 100%
Final Decking (Completed February 2024)
- By the grace of God, we raised 26 Million Naira and exceeded our goal of 20 Million naira by March 2024. We appreciate all those who helped us rase against the then inflation to complete this milestone. 130%
Long-term goal: Raise 300 Million naira by 2026
- Raise 300 Million Naira to build the IVCU Legacy Building by the year 2026 | Amount left to complete: 171.87 Million Naira 43%
Thank you for your support since we first launched the campaign. Work is progressing and we cannot achieve this alone. Let your contribution be a part of this extraordinary journey. Our goal is to raise 300 Million Naira to build the IVCU Legacy Building by the year 2026. As we embark on this remarkable mission, we trust God’s ability to grant us success and eventual completion. Join this great movement in IVCU and let your love for the house show through your donation.